How Does a Modular Home Get Assembled? – Part II: Set Day

Share this Post

The Day Begins

Set day is one of the few days that weather can impact modular construction when building a new home. A modular home is mostly finished on the inside including items such as: cabinets, trim, drywall, flooring, etc. If the weather forecast is calling for bad weather, a decision will be made to proceed or not. On occasion a decision is made to cancel a set or to delay it based on the mud that results from bad weather. All efforts are made to reschedule sets quickly. While disappointing, it is almost always the right decision to delay rather than chance introducing water and moisture into a home that has been built in a completely dry factory environment.

On the day of set, the set crew typically shows up at first light. Because a home’s modules are protected with shrink wrap and shielded with sheathing for protection during transport, it will take about 15 minutes or more per module for the set crew to remove it and prepare the module for set.

Related: THE REALITY OF HOME BUILDING: 5 THINGS TO THINK ABOUT

The crane show up in the morning and, depending on the counter-weights necessary, will take about 45 minutes to get set up. This process includes getting positioned, installing outrigger pads, installing counter-weight, and then installing spreader bars and cables. In some parts of the country, straps and clevis’ are used. In some other parts of the country, the modules can actually be “rolled” onto the foundation without the need for a crane. Regardless of the method used, the first module is typically ready to be placed on the foundation within 1-2 hours of first light.

Placement of the First Module

Blog - Modular Home assembly - P2 - First ModuleOnce modules are stripped of their protective packaging and the crane is “rigged and ready”, it’s time to get the first module on the foundation. However, prior to placing the first module on the foundation, the set crew has done many measurements on the foundation to determine if it is square and level. If there are any imperfections, decisions are made prior to lifting the first module as to how to fix or mitigate any issues.

The rigging process then begins. Rigging is the process by which straps or cables are attached to the module so that it can be safely lifted by the crane. It is critical to the rest of the home set that the first module is set perfectly, taking into account any foundation imperfections. Once that module is set, all other modules are lined up with it on the foundation.Blog - Modular Home assembly - P2 - First Module on Foundation
A key to getting the first module set correctly is by actually lifting it crooked. That may sound strange, but the module is lifted on such an angle that an outside corner will touch the foundation first. Second, the opposite outside corner touches the foundation and is then followed up with the interior section of the module touching the supports. As the crane lowers the module, more weight is placed on the foundation and the module comes to rest in its final location, all controlled and monitored by the set crew lead.

Is There a Second Story?

3screen1-up

 

As the process moves along, the modules are assembled much like a puzzle. The set crew is following instructions from the manufacturer which has typically labeled each module and provided a diagram or map as to how each piece is placed and fits together. If the home has a second floor, bolts or lag screws are typically called for and are placed at the ceiling connecting the first floor modules together. This helps make the extra strong bond between modules which makes a modular home much stronger than its typical site built counterpart.

Notice in the pictures that a separate bump out is lifted by the crane and then set on the foundation. The second floor modules, much like the first floor, are lifted on an angle and set/stacked precisely on the first floor modules. By lifting it so the interior walls meet last, the rigging cables are pinched when removed thereby making a nice, tight connection.

Raising the Roof

3screen2-up

 

On set day, the assembly process for the roof resembles that of a child’s Transformer® toy. Typically roofs are hinged so they can be folded up. Eaves or overhangs can be flipped down, and the gable ends of the home are assembled in pieces. With the last flip of the peak, a fully assembled roof appears. Because of this process, many or most of the shingles can be completed at the factory (depending on the roof design). While the roof set can be time consuming, the process quickly leaves a home weathered in and well protected from the elements.

Some Miscellaneous Thoughts

All Shapes and Sizes

Blog - Modular Home assembly - P2 - Misc 1For many, there is a preconceived notion that modular means boxy. However, modular design is flexible enough to encompass just about any style or type of home. From Chalets, to modern/contemporary architecture, to Victorian turrets; as long as it meets building code and can be transported legally it can be built using modular construction. When it comes to energy efficiency, factory quality construction can’t be beat for building tight, efficient homes.

 

Homes on Pilings

Blog - Modular Home assembly - P2 - Misc 2Modular homes can be placed on just about any type of foundation (except slabs… for now). Modular construction is great for coastal applications where homes must be placed high up to avoid storm surge. In fact, modular homes are built so strong that after Superstorm Sandy, modular construction surged in the area because it was a fast, cost effective method to replace damaged homes with a building system that is known for being inherently stronger than its site built counterpart.

End of Day 1 – Finishing Up the Set

Blog - Modular Home assembly - P2 - End of Day 1At the end of day one a typical modular home can be up and under roof. A less complex home with only two modules can be up and completely shingled in a day. For more complex homes, it may take two, three, or even more days to complete the set.

However long it takes, the home that is built in a factory at the exact same time as the site work was being completed is placed on a foundation and ready to begin the onsite finish. The set isn’t complete until all roof shingling is done and required attachments between modules and to the foundation are completed.

What is left is the finish to the areas of the home where modules meet, exterior finishes need applied or completed, utility connections, and other misc. items. In most cases, on site completion can be accomplished with 6 weeks of delivery to the site.

This concludes Part II of this two part post. Check out Part I to learn how the site was prepared for the modular units to arrive.

About the Author
Ken Semler

Ken Semler

Facebook Twitter

Hi, I am Ken Semler the founder of Impresa Modular. I am passionate about our company and the homes that we provide. Modern modular construction enables us to deliver healthy, safe, and energy-efficient living spaces. Impresa Modular is a licensed/registered/certified builder/contractor in almost every state. I believe that modular homes provide the best way to deliver virtually unlimited design flexibility at the greatest value.

Share this Post

Comments 6

    1. Ken Semler Post
      Author

      Ryan, Many of our customers bring their own custom home plans to us. That plan was brought to us by the customer and we “modularized” it and built it. That is actually how we build almost 70% of the homes we provide. We are a custom modular home builder. Thanks, Ken

  1. Justin Hammer
    1. Ken Semler Post
      Author

      Yes, actually many of our customers choose this option. While it isn’t actually a “shell” it is a little more than. We can do certain things very efficiently in a factory. That is why modular construction offers such a great value. We can build the floor, walls, and roof. We install the electric and plumbing and finish the drywall. We assemble a home on a foundation and have it dried in. We do the “heavy-lifting”. In some cases, our customer takes over from there and does their own trim, cabinets, floor, site connections, etc. Because of the cost effectiveness of modular construction, it is very hard to beat a factories buying power for cabinets, standard flooring, trim, etc. However, if you have a very particular taste the factory doesn’t offer or you are getting the materials at below market prices then it sometimes makes sense to do more of that onsite. We are very flexible in what we offer and the level of finish we can deliver our modules at.

  2. Hi Ken,
    I’m doing some research with these mod homes….can you pls school me on the foundations. My mom has always sworn by “cement foundations, or a concrete slab” foundations. She says they don’t give and they insulate a home better than anything else. Her current home is on a wood foundation and she hates it. She swears they give after about 10-15 years and result in a creaky, uneven mess. And she likes ceramic tile, and has never been able to do it on her home. Is she just crazy and stuck in the 50s or is there truth to this? I raise the question b/c I see that you all don’t build on slab foundations…

    1. Ken Semler Post
      Author

      Kris,
      I can’t comment on your mothers condition but let me elaborate on foundation systems. Many people don’t even know you can build using wood foundations. They are more common in the mid-west and plains states and are actually covered in the International Residential Code (IRC) book as a fully legitimate foundation type. When it comes to foundations for modular construction, we don’t have a standard way to put our homes on slabs. Modular homes are built to drop plumbing and electrical connections through the floor for connection and routing. This means we either need a crawlspace or a full basement to place modular homes on. How that foundation is constructed can be with ICFs, precast, concrete block, poured wall, etc. In most all cases, concrete based.
      I hope this helps!
      Ken

Leave a Reply

Your email address will not be published. Required fields are marked *